Cipher Digital Reviewed site records in the company’s own words.
EDGAR legal name Cipher Digital Inc.
SEC CIK 0001819989
Incorporated Delaware
Dossier version 1
Identity checked 2026-11-04 OBSERVED · LAST GOOD CHECK 2026-11-04, 20:27 ET
01 Sites 02 Power 03 Incentives 04 Water + permits 05 Policy exposure Timeline Coverage Corrections Sites Reviewed company site records Site Location MW Status as stated Source Black Pearl Facility Quote + record The Company has a 300 MW data center in Wink, Texas that draws power from the power grid (the “Black Pearl Facility”) that was used for bitcoin mining through February 2026, and in August 2026 commenced phased delivery to an HPC tenant. Wink, Texas · Cipher Digital Inc. — 10-Q Note 1 · SX-07-A-0001
Wink, Texas 300 operating (HPC phased delivery) 10-Q Note 1, Nature of operations 2026-11-02
Barber Lake Facility Quote + record the 300 MW Barber Lake Facility for Fluidstack USA II Inc. (“Fluidstack”), expecting phased commencement in the fourth quarter of 2026 not stated in source · Cipher Digital Inc. — 10-Q Note 1 · SX-07-A-0002
not stated in source 300 under constructionCOMPANY-STATED
10-Q Note 1, Nature of operations 2026-11-02
Stingray Facility Quote + record the 100 MW Stingray data center (the “Stingray Facility”) expecting commencement in 2027 not stated in source · Cipher Digital Inc. — 10-Q Note 1 · SX-07-A-0003
not stated in source 100 under constructionCOMPANY-STATED
10-Q Note 1, Nature of operations 2026-11-02
Odessa Facility Quote + record The Company also operates one wholly owned bitcoin mining data center, a 207 MW site located in Odessa, Texas that draws fixed priced power from a power purchase agreement with its electricity provider (the “Odessa Facility”). Odessa, Texas · Cipher Digital Inc. — 10-Q Note 1 · SX-07-A-0004
Odessa, Texas 207 operating (bitcoin mining) 10-Q Note 1, Nature of operations 2026-11-02
7 additional sites Quote + record The Company’s portfolio as of September 30, 2026 also consists of seven additional sites expected to be built out for HPC. not stated in source · Cipher Digital Inc. — 10-Q Note 1 · SX-07-A-0005
not stated in source not stated in source developmentCOMPANY-STATED
10-Q Note 1, Nature of operations 2026-11-02
Power NOT MONITORED No reviewed records supplied for this section. This is not a zero.
RECORD SX 07-C // INCENTIVES
Incentives NOT MONITORED No reviewed records supplied for this section. This is not a zero.
RECORD SX 07-D // WATER + PERMITS
Water + permits NOT MONITORED No reviewed records supplied for this section. This is not a zero.
RECORD SX 07-E // POLICY EXPOSURE
Policy exposure NOT MONITORED No reviewed records supplied for this section. This is not a zero.
Timeline RECORD SX 07-A // SITES // FILED 2026-11-02
COMPANY DISCLOSURE Black Pearl Facility -- 300 MW -- Wink, Texas -- bitcoin mining through February 2026; phased delivery to an HPC tenant commenced August 2026
Verbatim quote and source The Company has a 300 MW data center in Wink, Texas that draws power from the power grid (the “Black Pearl Facility”) that was used for bitcoin mining through February 2026, and in August 2026 commenced phased delivery to an HPC tenant. 10-Q Note 1, Nature of operations · Original source ↗
Cite: Seraphix Systems, “SX-07-A-0001”, v1, https://seraphixsystems.com/r/SX-07-A-0001 , retrieved 2026-11-05 . · JSON
RECORD SX 07-A // SITES // FILED 2026-11-02
COMPANY DISCLOSURE Barber Lake Facility -- 300 MW -- for Fluidstack USA II Inc. -- company expects phased commencement in Q4 2026
Verbatim quote and source the 300 MW Barber Lake Facility for Fluidstack USA II Inc. (“Fluidstack”), expecting phased commencement in the fourth quarter of 2026 10-Q Note 1, Nature of operations · Original source ↗
Cite: Seraphix Systems, “SX-07-A-0002”, v1, https://seraphixsystems.com/r/SX-07-A-0002 , retrieved 2026-11-05 . · JSON
RECORD SX 07-A // SITES // FILED 2026-11-02
COMPANY DISCLOSURE Stingray Facility -- 100 MW -- company expects commencement in 2027
Verbatim quote and source the 100 MW Stingray data center (the “Stingray Facility”) expecting commencement in 2027 10-Q Note 1, Nature of operations · Original source ↗
Cite: Seraphix Systems, “SX-07-A-0003”, v1, https://seraphixsystems.com/r/SX-07-A-0003 , retrieved 2026-11-05 . · JSON
RECORD SX 07-A // SITES // FILED 2026-11-02
COMPANY DISCLOSURE Odessa Facility -- 207 MW -- Odessa, Texas -- wholly owned bitcoin mining data center
Verbatim quote and source The Company also operates one wholly owned bitcoin mining data center, a 207 MW site located in Odessa, Texas that draws fixed priced power from a power purchase agreement with its electricity provider (the “Odessa Facility”). 10-Q Note 1, Nature of operations · Original source ↗
Cite: Seraphix Systems, “SX-07-A-0004”, v1, https://seraphixsystems.com/r/SX-07-A-0004 , retrieved 2026-11-05 . · JSON
RECORD SX 07-A // SITES // FILED 2026-11-02
COMPANY DISCLOSURE Seven additional sites expected to be built out for HPC
Verbatim quote and source The Company’s portfolio as of September 30, 2026 also consists of seven additional sites expected to be built out for HPC. 10-Q Note 1, Nature of operations · Original source ↗
Cite: Seraphix Systems, “SX-07-A-0005”, v1, https://seraphixsystems.com/r/SX-07-A-0005 , retrieved 2026-11-05 . · JSON
Coverage OBSERVED · LAST GOOD CHECK 2026-11-04, 20:45 ET
Source coverage and last good check Source Coverage Last good check SEC EDGAR · filings OBSERVED Filings for every pilot entity
2026-11-04, 20:45 ET EIA-930 · hourly grid demand OBSERVED ERCO, PJM, SOCO balancing areas
2026-11-04, 20:07 ET Statutes, codes + executive actions OBSERVED · MANUAL Primary text for ENACTED records in pilot states
2026-11-04 Press · secondary OBSERVED · MANUAL Named outlets only; replaced when a primary is attached
2026-11-04 State utility commission dockets NOT MONITORED PUCT, Georgia PSC, Virginia SCC
Not stated in source Large-load interconnection queues NOT MONITORED ERCOT, PJM, Georgia Power
Not stated in source Environmental + local permits NOT MONITORED TCEQ, Georgia EPD, Virginia DEQ, local land use
Not stated in source State + county incentive agreements NOT MONITORED Comptroller, revenue departments, county abatements
Not stated in source
Corrections No corrections supplied. Earlier versions remain visible when a correction is published.