RECORD SX 07-A // SITES // FILED 2026-02-11
COMPANY DISCLOSURERJ3 phase 2 -- Rio de Janeiro -- IBX data center project under construction as of December 31, 2025; target open date Q4 2026 (10-K, filed 2026-02-11)
Verbatim quote and source
RJ3 phase 2 Rio de Janeiro Q4 2026 550 46
10-K Item 1B. ITEM (normalized-text offset 241477) · Original source ↗
Supporting source
The following table presents a summary of our significant IBX data center projects under construction as of December 31, 2025: Property Property Location Target Open Date Sellable Cabinets Total Capex (in millions) (1)
table heading above this row · FILED · SEC EDGAR ↗
Cite: Seraphix Systems, “SX-07-A-0543”, v1, https://seraphixsystems.com/r/SX-07-A-0543, retrieved . · JSON