Barber Lake Facility SX-07-A-0002 | Cipher Digital | Mitchell 300 MW | air permit issued 2026-01-20 TCEQ public query | approved/executed (issuer statement) SEC EDGAR filing | energized (issuer statement) second quarter of 2025 SEC EDGAR filing |
|---|
Black Pearl Facility SX-07-A-0001 · SX-07-B-0006 | Cipher Digital | not stated 300 MW | Not confirmed | approved/executed (issuer statement) SEC EDGAR filing | energized (issuer statement) SEC EDGAR filing |
|---|
Colchis Site SX-07-A-0064 | Cipher Digital | not stated | No public source found | approved/executed (issuer statement) SEC EDGAR filing | targeted (issuer statement) in 2028 SEC EDGAR filing |
|---|
McLennan Site SX-07-A-0319 | Cipher Digital | not stated 500 MW | No public source found | ERCOT Batch Zero: conditional studied load classification (issuer statement) SEC EDGAR filing | targeted (issuer statement) in 2028 SEC EDGAR filing |
|---|
Mikeska Site SX-07-A-0320 | Cipher Digital | not stated 500 MW | No public source found | ERCOT Batch Zero: conditional studied load classification with PCLR designation (issuer statement) SEC EDGAR filing | targeted (issuer statement) in 2028 SEC EDGAR filing |
|---|
Milsing Site SX-07-A-0321 | Cipher Digital | not stated 500 MW | No public source found | No public source found | targeted (issuer statement) between 2028 and 2029 SEC EDGAR filing |
|---|
Odessa Facility SX-07-A-0004 | Cipher Digital | not stated 207 MW | No public source found | mentioned (issuer statement) SEC EDGAR filing | energized (issuer statement) SEC EDGAR filing |
|---|
Reveille Facility SX-07-A-0490 | Cipher Digital | not stated | No public source found | approved/executed (issuer statement) SEC EDGAR filing | targeted (issuer statement) for 2027 SEC EDGAR filing |
|---|
Austin, Texas SX-07-A-0254 | Core Scientific | not stated | No public source found | utility service in place: Austin Energy general tariff (issuer statement) SEC EDGAR filing | energized (issuer statement) second quarter of 2024 SEC EDGAR filing |
|---|
Cedarvale Facility SX-07-A-0513 | Core Scientific | Ward | No public source found | No public source found | No public source found |
|---|
Cottonwood 1 facility SX-07-A-0512 | Core Scientific | not stated | No public source found | utility contract in place: Texas-New Mexico Power, 253 MW contracted capacity (issuer statement; Cottonwood campus-level) SEC EDGAR filing | energized: 50MW energized capacity at COT1 (issuer statement) SEC EDGAR filing |
|---|
Denton, Texas SX-07-A-0217 | Core Scientific | not stated | Not confirmed | ERCOT conditional approval: Base Load, Pathway (a), 297 MW (issuer statement) SEC EDGAR filing | energized (issuer statement) prior to March 25, 2022 SEC EDGAR filing |
|---|
Hunt County, Texas SX-07-A-0179 · SX-07-A-0557 | Core Scientific | Hunt 430 MW | Not confirmed | approved/executed (issuer statement) SEC EDGAR filing | No public source found |
|---|
Pecos, TX SX-07-A-0172 · SX-07-B-0003 | Core Scientific | not stated | Not confirmed | ERCOT Batch Zero conditional approval: Base Load, Pathway (b), 300 MW (issuer statement) SEC EDGAR filing | energized (issuer statement) after March 25, 2022 and before July 10, 2026 SEC EDGAR filing |
|---|
Horizon 1 SX-07-A-0497 | IREN | Childress | halted by state order 2026-09-21 SEC EDGAR filing | approved/executed: grid connection agreement for the Childress campus (issuer statement; campus-level) SEC EDGAR filing | energized (issuer statement) August 2026 SEC EDGAR filing |
|---|
Horizon 2 SX-07-A-0498 | IREN | Childress | halted by state order 2026-09-21 SEC EDGAR filing | approved/executed: grid connection agreement for the Childress campus (issuer statement; campus-level) SEC EDGAR filing | targeted (issuer statement) calendar Q4 2026 SEC EDGAR filing |
|---|
Horizon 3 SX-07-A-0499 | IREN | Childress | halted by state order 2026-09-21 SEC EDGAR filing | approved/executed: grid connection agreement for the Childress campus (issuer statement; campus-level) SEC EDGAR filing | targeted (issuer statement) calendar Q4 2026 SEC EDGAR filing |
|---|
Horizon 4 SX-07-A-0500 | IREN | Childress | halted by state order 2026-09-21 SEC EDGAR filing | approved/executed: grid connection agreement for the Childress campus (issuer statement; campus-level) SEC EDGAR filing | targeted (issuer statement) calendar Q4 2026 SEC EDGAR filing |
|---|
Sweetwater 1 SX-07-A-0531 | IREN | not stated 1400 MW | No public source found | approved/executed: grid connection agreement (issuer statement) SEC EDGAR filing | substation energized (issuer statement) SEC EDGAR filing |
|---|
Sweetwater 2 SX-07-A-0532 | IREN | not stated 600 MW | Not confirmed | approved/executed: 600MW grid connection agreement with AEP Texas Inc. (issuer statement) March 17, 2025 SEC EDGAR filing | targeted: substation energization (issuer statement) fourth quarter of calendar year 2027 SEC EDGAR filing |
|---|