Cipher Barber Lake has received approvals for 300 MW of interconnection without any restrictions on the load profile and has entered into agreements necessary to participate in the Electric Reliability Council of Texas ("ERCOT") market.
Dossier records do not store a document hash, a fetch time or a listing hash, so a download cannot be compared byte for byte. Check the quote on this page against the document at the link instead.
Seraphix does not fetch the document when you open this page.
The dates above are the ones stored with the record, unchanged.
Texas site tracker
Site milestones
Barber Lake Facility
Permit
air permit issued · 2026-01-20 Date: TCEQ NSR project complete date (first registration of this permit number)
TCEQ NSR permit 182754 type PBR (30 TAC 106.511) status EFFECTIVE; project 403704 'PBR NEW REGISTRATION' INITIAL received 01/20/2026 complete 01/20/2026; customer CIPHER BARBER LAKE LLC; RN RN112273891 'BARBER LAKE DATA CENTER PROJECT', MITCHELL County
TCEQ public query · Source Link to company: TCEQ customer 'CIPHER BARBER LAKE LLC' = Ex.21 subsidiary 'Cipher Barber Lake LLC' (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/exh211subsidiariesasof1231.htm); site term 'Barber Lake' in RE name/location
Interconnection
approved/executed (issuer statement)
Cipher Barber Lake has received approvals for 300 MW of interconnection without any restrictions on the load profile and has entered into agreements necessary to participate in the Electric Reliability Council of Texas (“ERCOT”) market.
SEC EDGAR filing · 10-K filed 2026-02-24 · Source Link to company: site name 'Barber Lake' in Cipher Digital's own filing (CIK 0001819989)
Energized
energized (issuer statement) · second quarter of 2025 Date: date phrase adjacent to the milestone phrase in the quote
The increase in the three months ended June 30, 2025 is driven primarily by additional power costs from the energization of the Black Pearl and Barber Lake facilities in the second quarter of 2025.
SEC EDGAR filing · 10-Q filed 2025-08-07 · Source Link to company: site name 'Barber Lake' in Cipher Digital's own filing (CIK 0001819989)
Live since 2026-11-13 -- each milestone shows only what a public record states. A milestone is shown only when its source links the site to the tracked company: the company's own SEC filing names the site, or the permit holder is the company's subsidiary listed in its Exhibit 21 (filing cited). A name match alone never counts. 'No public source found' means no checked source shows the milestone; 'Not confirmed' means a source exists but its link to the company is not yet proven, so nothing from it is shown. Nothing is inferred. All Texas sites
Version history
v1Barber Lake Facility -- 300 MW -- for Fluidstack USA II Inc. -- company expects phased commencement in Q4 2026 · SUPERSEDED · REASON Location added: the 10-Q quote names no place; Cipher's FY2025 10-K (filed 2026-02-24) states the Barber Lake site is located near Colorado City, Texas (supporting quote). Claim and main quote unchanged. · SOURCE Correction source
v2 (current) Barber Lake Facility -- 300 MW -- for Fluidstack USA II Inc. -- company expects phased commencement in Q4 2026