In January 2026, Vistra announced it had entered into 20-year PPAs with Meta, pursuant to which the Company has agreed to supply Meta with a total of 2,609 MW of carbon-free power and capacity from the Company's PJM nuclear power plants as follows:
Seraphix Systems. “SX-07-B-0016” (version 2). RECORD SX 07-B // POWER // FILED 2026-11-09. Published by Seraphix 2026-11-10. Seraphix record: https://seraphixsystems.com/r/SX-07-B-0016. Primary document: https://www.sec.gov/Archives/edgar/data/1692819/000169281926000025/vistra-20260930.htm. Fetched date: not recorded.
BibTeX
@misc{seraphix-SX-07-B-0016-v2,
author = {{Seraphix Systems}},
title = {SX-07-B-0016: RECORD SX 07-B // POWER // FILED 2026-11-09},
howpublished = {\url{https://seraphixsystems.com/r/SX-07-B-0016}},
version = {2},
year = {2026},
date = {2026-11-10},
note = {Primary document: \url{https://www.sec.gov/Archives/edgar/data/1692819/000169281926000025/vistra-20260930.htm}. Fetched date not recorded.}
}
Dossier records do not store a document hash, a fetch time or a listing hash, so a download cannot be compared byte for byte. Check the quote on this page against the document at the link instead.
Seraphix does not fetch the document when you open this page.
The dates above are the ones stored with the record, unchanged.
Version history
v1PPAs with Meta -- 2609 MW -- term 20-year -- from PJM nuclear power plants -- January 2026 · SUPERSEDED · REASON Ingest date corrected: the source filing (accession 0001692819-26-000025, filed 2026-11-09) was first stored 2026-11-09T12:05:03Z; this record had shown the release-wide date 2026-11-04, before the filing existed (site QA 2026-11-12). Claim, quote and source are unchanged. Chairman approval 2026-11-12 18:58 ET. · SOURCE Correction source
v2 (current) PPAs with Meta -- 2609 MW -- term 20-year -- from PJM nuclear power plants -- January 2026